Each job, from start to finish
The same four stages on every contract, in the monthly board pack.
Tender
The estimate split into labour, materials, plant and subcontract, so the job is costed against it from the first week.
Stage payments
A construction contract of 45 days or more gives a right to stage or periodic payments (Housing Grants, Construction and Regeneration Act 1996, section 109). The forecast carries each application and its due date.
Work in progress
Each month, cost to date compared with the value of work done on every live job, so the monthly profit matches the work on site.
Final account and retention
The retention held by the client recorded as owed to you, with the date each part is due, and chased on that date.